Construction Plan Expedites Repair on I-5

The innovative plan calls for approximately two weeks of lane and ramp restrictions to each direction of I-5 from the Capitol City Freeway /U.S. Highway 50 interchange to Richards Boulevard, so contractors can replace freeway drainage and pavement. After curing, an additional week of lane and ramp restrictions will take place to allow time for the contractor to apply a polyester sealant. This quick fix will allow the contractor to finish work months ahead of schedule. Construction begins May 30th at 8 p.m.